Renovated dining room with the new fireplace wall, LED lighting and vinyl plank flooring

Residential Care Facility Renovation

The GardensBooneville

About the project

An aging residential care facility in Booneville became a bright, updated home for The Gardens of Arkansas.

CCG renovated 24 resident bedrooms, their bathrooms and every common area of the facility, starting with a site visit and due diligence report that found what a paint-and-flooring scope would have missed.
The Gardens of Arkansas asked for new paint and flooring at its Booneville facility. CCG’s site visit showed the building needed more than that.

Before pricing the job, CCG walked the building and delivered a site visit and due diligence report, room by room and with photos. It flagged cracks in the slab, bathroom vanities too large for code clearances, toilets of mixed styles and heights, mismatched and ungrounded outlets, dated fluorescent and halogen lighting, five different door types, and fire and life safety items to confirm with the state licensing office. Each finding came with a recommendation and an open question, so The Gardens could settle the scope up front instead of paying for rework later.

With those decisions made, CCG prepped and leveled the floors and installed new vinyl plank across 13,770 SF, then patched, primed and painted more than 50,000 SF of walls and ceilings. Ceiling fans in the bedrooms and dining room gave way to new LED fixtures, closets got new lighting circuits, and the exterior got new soffit lights and LED wall packs. Emergency and exit lighting was added, along with outlets for televisions, cameras and access control.

In the bathrooms, CCG replaced toilets, exhaust fans, mirrors, faucets, shower heads and accessories, and swapped out four vanities that were rotted beyond repair. The dining room got a new wall opening and a fireplace wall with decorative tile, and the job wrapped up with new room signs, a monument sign, painted exterior doors and a full facility cleaning.

Dining room during the August site visit, with VCT floors and fluorescent fixtures

Before Construction

Where It Started

At the August site visit, the building was showing its age: worn tile over a cracked slab, mismatched outlets and switches, ceiling fans as the only light in the bedrooms, and dated fixtures in every bathroom.
Resident hallway during the site visitResident bathroom during the site visit, with dated vanity and fixturesKitchen during the site visitCrack in the concrete slab found during the site visitCCG crew preparing a bedroom floor for new vinyl plankOld floor tile removed in a common areaDrywall patched and primed in a resident bathroomFloor leveler poured before new flooringResident bedroom during the site visit, with a ceiling fan as the only light

“

Discuss your next project

Have a building that needs a second life?

Tell us about the property, the schedule, and what has to happen on site. We’ll walk you through how CCG would approach it.

The Gardens, Booneville
Renovation13,770 SFCompleted 2026